Metalworking

EMAG USP 21-450

Spindle
EMAG USP 21-450
Client
«ОАО Газпромтрубинвест — Волгореченский трубный завод»
Repair time
1 months
History

Repair of large spindles has long been the norm for us and the EMAG USP 21-450 l is no exception. It would seem that another EMAG is in our portfolio, but we have not yet encountered a burnt-out stator. In order to return the spindle to working condition, we rewound the stator, replaced the seals and cable protection, washed the parts, assembled, tested and packed.

Problem
The stator burned out
Dismantling time
1 day
Disassembly time
2 days
Assembly time
3 days